detailed information
Wastewater Treatment Plant for Briceni
- Identification number: MD-2016-079-FO-14050
- Total anticipated budget: 47 698 575 CZK
- Implementation period: 2016 - 2022
- Project location: Moldova
- Sector: Water and Sanitation
- Grant, public tender and budgetary measure within the project:
Tender: Feasibility study for wastewater treatment plant in Briceni
Implementation period: 2016
Implementing partner: TÜV Rheinland Česká republika s.r.o.
Financial resources provided by CzDA in 2016: 356 950 CZKTender: Camera survey of the sewage system in Briceni
Implementation period: 2017
Implementing partner: Lukáš Hladík
Financial resources provided by CzDA in 2017: 452 007,50 CZKTender: Translation of the feasibility study for wastewater treatment plant in Briceni into Czech
Implementation period: 2017
Implementing partner: Lingea s.r.o.
Financial resources provided by CzDA in 2017: 27 771 CZKTender: Výstavba čistírny odpadních vod
Implementation period: 2019-2023
Implementing partner: WWTP Briceni (Ircon, s.r.o., EKOSYSTEM spol. s r.o.)
Budget for the year 2019: 5 767 901,50 CZK
Budget for the year 2020: 25 379 555,37 CZK
Budget for the year 2021: 18 958 569,03 CZK
Planned budget for the year 2022: 3 866 912,41 CZK
Planned budget for the year 2023: 135 750,- CZK
The town of Briceni has approached the Czech Republic with a request for cooperation in improving the quality of groundwater and surface water. The problems are mainly caused by inadequate wastewater management and an outdated sewerage network, much of which was built in the 1970s. Due to limited maintenance, wastewater leaks into the soil and groundwater. The project aims to construct a wastewater treatment plant as well as to reconstruct the pumping stations and the sewerage network.
The construction of the wastewater treatment plant for 5,000 equivalent inhabitants started in August 2019. On 28 February 2022, the newly constructed treatment plant was handed over to the beneficiary for operation, with a one-year test run commencing at the same time. In parallel, the main pumping station was technologically equipped, while the city financed the reconstruction of the outdoor part of the station.